The recent decision of LHRE Group Pty Ltd v Complete Hire & Sales Pty Ltd [2025] WADC 81 (LHRE v Complete) highlights the importance of a respondent “speaking up” on receipt of a statutory payment claim, especially if the status of the claimant or the contract is in question. The case serves as a reminder that a respondent who does not “speak up” may have to “pay up” under security of payment legislation, the Building and Construction Industry (Security of Payment) Act 2021 (WA) (SOP Act).
Whilst Complete was initially successful in avoiding an application for summary judgment by LHRE for a statutory debt (see LHRE Group Pty Ltd v Complete Hire & Sales Pty Ltd [2024] WADC 61),[1] the Court in LHRE v Complete found that a construction contract existed, the SOP Act applied, and Complete became liable to pay the full amount claimed.
LHRE Group Pty Ltd v Complete Hire & Sales Pty Ltd [2025] WADC 81
LHRE v Complete considered a situation where the recipient of a payment claim made pursuant to the SOP Act did not give a payment schedule in response to the payment claim because it believed that:
LHRE Group Pty Ltd (LHRE) is a labour hire company for discrete works on construction projects. LHRE’s sister company, OSB Group Pty Ltd (OSB), is a contractor that performs construction works on mining projects.[2] Complete Hire & Sales Pty Ltd (Complete) provides building services to a variety of clients, including its related entities such as Spinifex Holdings (WA) Pty Ltd (Spinifex Holdings) which operates the Spinifex Hotel in Derby, WA.[3]
Kevin O’Shea (Kevin) is the sole director of both LHRE and OSB, and Michael O’Shea (Michael) is the general manager of both LHRE and OSB.[4] Emanuel Dillon (Dillon) is the sole director of Complete, and the sole director of Spinifex Holdings.[5]
In May 2023, Complete had discussions with Kevin and Michael in relation to the construction of a 200-person camp in Onslow and, separately, for labour hire for rectification and refurbishment works at the Spinifex Hotel.[6] Labour arrived at the Spinifex Hotel and undertook rectification and refurbishment works from 1 to 18 June 2023.[7] After the project concluded, Complete received:
Dillon requested numerous changes to the invoice and it was re-issued several times as a result. However, amidst his requests, Dillon did not raise concerns about the invoice having been issued by LHRE rather than OSB.[9]
On 2 October 2023, LHRE issued a statutory payment claim under the SOP Act for $81,934.64, including GST. Complete did not give any payment schedule in response to the statutory payment claim, nor did Complete pay the claimed amount by 6 November 2023, (which was the due date for payment under s 20(1)(b) of the SOP Act).[10]
The primary issue for determination before the Court was the identity of the entity with whom Complete entered the construction contract, agreement or other arrangement. At trial, Complete contended that it had entered into a contract with OSB, not LHRE.[11]
A secondary issue was whether LHRE had assigned its interest to Scottish Pacific (BFS) Pty Ltd (ScotPac) (noting the statement on the invoice that amounts payable had been transferred to ScotPac).[12]
During the trial, Kevin and Michael of LHRE and OSB were found to be “credible witnesses, doing their best to provide the court with their honest recollection”,[13] while Dillon of Complete was “an unimpressive witness and most of his evidence could not be confidently relied upon by the court unless corroborated by contemporaneous documents”.[14]
The Court could not use the traditional approach of offer and acceptance to identify whether a contract existed (whether between LHRE and Complete, or between OSB and Complete) because the contractual negotiations proceeded “organically, informally, and relatively quickly over a matter of days” and the parties “appeared to struggle to ensure formal matters were properly addressed”.[15] Instead, the Court undertook a “more complex and involved analysis”,[16] objectively assessing the intent conveyed by the parties’ words and actions in the context of the surrounding circumstances, with reference to the purpose and object of the transaction.[17]
Significantly, the Court found that Complete’s argument that it had assumed it was contracting with OSB because emails it received were sent using OSB email addresses and OSB signature footers was not supported by the evidence before the Court as to the parties' words, conduct and knowledge.[18] Relevantly:
The Court held that mobilisation of personnel onsite evidenced that there was mutual assent to all essential terms of an agreement between LHRE and Complete and in all of the circumstances, a reasonable person would consider LHRE and Compete had entered into a contract by 1 June 2023.[24]
The Court concluded there was no assignment of the debt from LHRE to ScotPac.[25]
The automated generic invoice containing a statement requiring payment to be made to ScotPac was not, without further evidence, sufficient to establish an assignment of the debt. Further, a letter from ScotPac confirmed that no assignment was made to ScotPac because the credit application process was never executed by Complete.
The Court held that LHRE and Complete entered into a construction contract and the statutory scheme of the SOP Act applied. LHRE served a statutory payment claim on Complete, but Complete did not respond with a payment schedule (or at all). Consequently, Complete became liable to pay the claim as it were admitted in full pursuant to s 26 of the SOP Act.[26]
Complete was awarded $81,934.64 plus interest at a rate of 6% per annum from the payment due date of 6 November 2023 as well as costs.
This article was written by Julia Millar Special Counsel, Briony Whyte Senior Associate and Matthew Endo Solicitor at Jackson McDonald.
If you need assistance understanding the provisions of the SOP Act or the terms of your contract, reach out to our Projects, Infrastructure + Construction team.
---
[1]https://www.jacmac.com.au/insights/dont-get-caught-out-what-you-need-to-know-before-applying-for-summary-judgment-for-a-sop-act-statutory-debt/
[2] LHRE Group Pty Ltd v Complete Hire & Sales Pty Ltd [2025] WADC 81 at [1] and [61].
[3] LHRE Group Pty Ltd v Complete Hire & Sales Pty Ltd [2025] WADC 81 at [2].
[4] No disrespect is intended in referring to Kevin O’Shea and Michael O’Shea by their first names.
[5] No disrespect is intended in referring to Emanual Dillion by his last name.
[6] LHRE Group Pty Ltd v Complete Hire & Sales Pty Ltd [2025] WADC 81 at [5]–[7].
[7] LHRE Group Pty Ltd v Complete Hire & Sales Pty Ltd [2025] WADC 81 at [10].
[8] LHRE Group Pty Ltd v Complete Hire & Sales Pty Ltd [2025] WADC 81 at [11].
[9] LHRE Group Pty Ltd v Complete Hire & Sales Pty Ltd [2025] WADC 81 at [13], [214].
[10] Being 25 business days after the payment claim was made.
[11] LHRE Group Pty Ltd v Complete Hire & Sales Pty Ltd [2025] WADC 81 at [27].
[12] LHRE Group Pty Ltd v Complete Hire & Sales Pty Ltd [2025] WADC 81 at [30].
[13] LHRE Group Pty Ltd v Complete Hire & Sales Pty Ltd [2025] WADC 81 at [129].
[14] LHRE Group Pty Ltd v Complete Hire & Sales Pty Ltd [2025] WADC 81 at [130].
[15] LHRE Group Pty Ltd v Complete Hire & Sales Pty Ltd [2025] WADC 81 at [187].
[16] LHRE Group Pty Ltd v Complete Hire & Sales Pty Ltd [2025] WADC 81 at [27]
[17] LHRE Group Pty Ltd v Complete Hire & Sales Pty Ltd [2025] WADC 81 at [189].
[18] LHRE Group Pty Ltd v Complete Hire & Sales Pty Ltd [2025] WADC 81 at [190].
[19] LHRE Group Pty Ltd v Complete Hire & Sales Pty Ltd [2025] WADC 81 at [203].
[20] LHRE Group Pty Ltd v Complete Hire & Sales Pty Ltd [2025] WADC 81 at [214]-[215]
[21] LHRE Group Pty Ltd v Complete Hire & Sales Pty Ltd [2025] WADC 81 at [216].
[22] LHRE Group Pty Ltd v Complete Hire & Sales Pty Ltd [2025] WADC 81 at [221].
[23] LHRE Group Pty Ltd v Complete Hire & Sales Pty Ltd [2025] WADC 81 at [223].
[24] LHRE Group Pty Ltd v Complete Hire & Sales Pty Ltd [2025] WADC 81 at [238]–[239].
[25] LHRE Group Pty Ltd v Complete Hire & Sales Pty Ltd [2025] WADC 81 at [244].
[26] LHRE Group Pty Ltd v Complete Hire & Sales Pty Ltd [2025] WADC 81 at [250]–[252].